New-Campus.jpg

NEW CAMPUS

Updates

Since our beginning in 2003, we have rented facilities from churches for our classes and we have continued to grow year after year. And now, we are out of room. Over 340 students fill out all the spaces on the church campus and our adjacent high school building. Through the generosity of His people, God has provided mightily for our school in the past couple years, allowing us to pursue our vision for a K-12 campus for over 600 students. 

1212 WARRIOR WAY CAMPUS

In 2003, we joined a national movement to “repair the ruins” of our culture and the Judeo Christian values upon which our nation was founded. Christ-centered classical education here at Trinity seeks to raise up generations of young people who are instilled with biblical wisdom, Christ-centered virtue, and a commitment to servant leadership. 

Trinity Christian School exists for these purposes and we are at a significant moment in our history. Since our beginning in 2003, we have rented facilities from churches for our classes and we have continued to grow year after year. And now, we are out of room. Over 340 students fill out all the spaces on the church campus and our adjacent high school building. Through the generosity of His people, God has provided mightily for our school in the past couple years, allowing us to pursue our vision for a K-12 campus for over 600 students. 
 

New Campus Map.jpg
Untitled-3.jpg

BUILDING UPDATES

May 26, 2021
May 26, 2021

press to zoom
May 26, 2021
May 26, 2021

press to zoom
May 26, 2021
May 26, 2021

press to zoom
May 26, 2021
May 26, 2021

press to zoom
1/13

May 26, 2021:

The parking lots have been paved, and cabinets are being installed in the classrooms. 

May 19, 2021:

Here are the most recent photos of the site as it is taking shape for us to move in at the beginning of July. 

April 20, 2021:

Progress continues on both the interior and exterior of the Upper School and Office Building!

April 13, 2021:

Sheetrock and insulation are going in and roofing is being installed.

March 9, 2021:

Progress continues in our new campus! Doors and windows are being installed.

February 24, 2021:

Trusses are on, and plumbing, electrical and HVAC are in progress!

January 12, 2021:

The light is going in within the next few weeks and the street name will officially be up. 

The second floor of the classroom building has been framed and now HVAC is going in and roofing is coming soon. The office has been completely framed and roof trusses are coming this next week.

December 30, 2020:

 

The Office Building is framed. And we are moving into the second floor framing of the Upper School Classroom Building. 

December 18, 2020:

 

Classroom Building Update: Floor joists are arriving and being installed this week with second story framing coming next. 

 

Office Building Update: Concrete being poured, framing starts next week.  

December 3, 2020:

The framing is coming up, it is exciting to see our dream taking shape. Praise the Lord for His goodness!

November 24, 2020:

 

Footings dug, cement slab poured, and elevator shaft construction began on the first classroom building . . . AND framing has begun!

November 23, 2020:

 

The Upper School Classroom Building is ready to start framing this week or next!